2/13/2015 - JCP&L Planned Outage – CONFIRMED FOR FRIDAY 2/13
As part of the Rocktown project, sub transmission lines need to be rebuilt. The sub transmission line that will have the outage,  feeds three substations south of Rocktown sub.  The Moore substation serves customers in West Amwell Twp. and Hopewell Township.  The planned outage will begin at 12:01 AM Friday, February 13th and will be restored by 6AM Friday, February 13th . JCP&L will send out a phone call to alert these customers of the planned outage on Wednesday, February 11th.